|
Let The Code Decide / Quik Talk (2002 NEC)
In 1994 after being an electrical inspector for more than six years, question after question was asked about swimming pools and other questions on code, so I decided to write down the answers and hand them out. The first Quik Talk article I wrote was about ground rods at a pool site. It went over well with inspectors and contractors, so I decided to continue with the Quik Talk. This section is for those who want to go back before the 2005 NEC. Throughout the years, the NEC has made changes every three years to make a better and safer electrical system. Who knows, you might find the answer you were looking for.
Do you want to know in advanced about Seminars & Continuing Education Classes?
"The State of Georgia is STILL on the 2005 NEC"
All questions below are answered under the 2002 NEC before adoption of the 2005 NEC
Computer & 15 amp circuit 12/7/2005
Given a processor, and monitor, how many computers should I install on a single 15 amp circuit?
Paul
You can figure that question out by reading the amp load on the label for each piece of equipment you have. Lets say one processor pulls 2 amps and one monitor pulls 2 amps. The total will be 4 amps. Article 210.20(A) shows a continuous load shall be 125%. 4 amps X 125% = 5. 15 amp breaker divided by 5 = 3 sets of equipment. A 20 amp breaker will allow 4 sets. Get it?
6 circuit rule 12/7/2005
Hello Mr. Stubbs -
I hope this is an easy one...
We're selling our 1978 home. It's currently in escrow and we've just
received a copy of the buyer's inspection results. The inspector has noted
that the main panel requires a main disconnect breaker because the home has
more than 6 branch circuits. This home has never had a main breaker and has
always had more than 6 branch circuits. Is there an exception to this " >6
circuit" rule? If so, could you please let me know where I could get a copy
of the dialog. I plan to review this information with the buyer's inspector
& real estate agent.
My panel doesn't support a main breaker. If I must install a main breaker,
could I simply mount an auxiliary main breaker box adjacent to the existing
panel with the appropriate conduit, ground bonding etc.? Would this
workaround pass inspection?
Thank you in advance for your response.
Greg
There is no exception for your existing installation. I have no clue why your home passed the first inspection, unless your local jurisdiction has an ordinance. I don't know how many breakers that you have in the panelboard, but it is a violation of article 230.71.
230.71 Maximum Number of Disconnects.
(A) General. The service disconnecting means for each service permitted by 230.2, or for each set of service-entrance conductors permitted by 230.40, Exception Nos. 1, 3, 4, or 5, shall consist of not more than six switches or sets of circuit breakers, or a combination of not more than six switches and sets of circuit breakers, mounted in a single enclosure, in a group of separate enclosures, or in or on a switchboard. There shall be no more than six sets of disconnects per service grouped in any one location. For the purpose of this section, disconnecting means used solely for power monitoring equipment, or the control circuit of the ground-fault protection system or power-operable service disconnecting means, installed as part of the listed equipment, shall not be considered a service disconnecting means.
You can have a main installed next to the panelboard if it outside. If the panelboard is inside, a main disconnect must be installed outside with a four wire feeder cable to the panel inside. You need to get with an electrician to work out the details of the installation. Make the home safe for sell.
Single conductor 12/8/2005
May a 240 volt circuit be installed in the same conduit with 120 volts and 277 volt circuits ?
Yes it can! The wiring shall have the same insulation rating if it is installed in the same cable or raceway. The rating cannot be lower then the highest rated conductor voltage being used in the same cable or raceway.
300.3 Conductors.
(C) Conductors of Different Systems.
(1) 600 Volts, Nominal, or Less. Conductors of circuits rated 600 volts, nominal, or less, ac circuits, and dc circuits shall be permitted to occupy the same equipment wiring enclosure, cable, or raceway. All conductors shall have an insulation rating equal to at least the maximum circuit voltage applied to any conductor within the enclosure, cable, or raceway.
Max. amp of Sub-panel 12/18/2005
Mr. Stubbs,
I came across your web site, and I was curious to know if the NECA
specifies a maximum allowable ampacity for sub-panels as compared to the
main panel that they are connected to.
For example, if a residence has a 200-amp service to a 200-amp main
panel, what is the allowable ampacity of any connected sub-panels? Would it
be allowable to have a 100-, 125-, 150-, or even 200-amp sub-panel?
What about multiple sub-panels? Would it be allowable to have:
1) two 100-amp sub-panels?
2) two 150-amp sub-panels?
3) a 125-amp and two 40-amp sub-panels
With the combinations above, there would still be space for plenty of
branch circuits in what would appear to be an already heavily loaded main panel.
I haven't really seen any discussion of this anywhere. I look forward
to hearing your response.
Jeremy
This is a good question, but let me clear up your question. Can you have a 200 amp main service, (outside I assume) and connect as many combination sub-panels down stream as long as they don't exceed 200 amps? The answer to that question is no. The sub-panels would not have the proper protection on the enclosures. If you do want a number of sub-panels down stream of the main, they all shall comply with Article 240.21(B)(1) and (B)(2) on the 10 & 25 foot tap rule, and Article 215.3. They also shall terminate to a single overcurrent device for that sub-panel. You may also have multiple sub-panels down stream without a main in the sub-panel if they have the same rating or greater then the main overcurrent device, but you cannot exceed the combination branch circuits connected loads that would cause the 200 amp main to trip. Even if you loaded them up, it doesn't mean you have exceeded the load on the main.
240.21 Location in Circuit.
Overcurrent protection shall be provided in each ungrounded circuit conductor and shall be located at the point where the conductors receive their supply except as specified in 240.21(A) through (G). No conductor supplied under the provisions of 240.21(A) through (G) shall supply another conductor under those provisions, except through an overcurrent protective device meeting the requirements of 240.4.
215.3 Overcurrent Protection.
Feeders shall be protected against overcurrent in accordance with the provisions of Part I of Article 240. Where a feeder supplies continuous loads or any combination of continuous and noncontiguous loads, the rating of the overcurrent device shall not be less than the noncontiguous load plus 125 percent of the continuous load.
Branch circuit not long enough 11/29/2005
Hello
I hope you can help. I want to move my service panel in the basement because of a leak I need to repair that is dripping on the service panel.
The branch circuits won't be long enough!
Can I use a junction box to splice the branch circuits and make them long enough to reach the service panels new location.
Thanks
Curtis
Yes you can! Just make sure the junction box that you install is big enough for all of the conductors you relocate. All of the equipment grounds have to be bonded together in the junction box or boxes and at least one shall be bonded to the metal enclosure if you don't use a plastic box. The neutrals of different circuits shall not be connected together. Go to Table 314.16(A) for box size and Table 314.16(B) for the square inches of the conductors.
Wire size 11/25/2005
What size wire the support a 100 amp breaker.
Using the 60 degree column on table 310.16 for copper and aluminum, 1 AWG copper and 1/0 aluminum. This will be the smallest conductor you can use on this table. There is an exception for single phase dwellings on table 310.15(B)(6).
Table 310.15(B)(6) Conductor Types and Sizes for 120/240-Volt, 3-Wire, Single-Phase Dwelling Services and Feeders. Conductor Types RHH, RHW, RHW-2, THHN, THHW, THW, THW-2, THWN, THWN-2, XHHW, XHHW-2, SE, USE, USE-2
For a 100 AMP breaker = 4 AWG copper or 2 AWG aluminum.
Changing supply conductors 11/18/2005
Hello Mr. Stubbs,
My house was built in 1979 in New Jersey and has a 40 degree wire rating ( which I found on the circuit breaker box). I just recently purchased a ceiling light fixture which states to make sure your dwelling has a 90 degree wire rating. How do you upgrade supply conductors, is this something that MUST be done by an electrician and if so what is the approx. range of cost for such?
Thanks
Andrea
Well Andrea, as always, I will always suggest that an electrician handle all wiring in any home or structure. Secondly, I can never quote or suggest a price on any electrical system. There are 50 States and hundreds of thousands of contractors.
First, the circuit breaker marked 40 degree is only the rating of the beaker. The wiring in the wall has a 60 degree or 90 degree rating on it. The reason for the 90 degree rating is for heat dissipation from the light bulb. If the heat is to high, the insulation can be damaged. The higher the wattage on the bulb, the higher the heat dissipation. Save your money and keep the wattage at 60 watts or less or have the electrician check the rating on the conductor. They may already be 90 degree rated
Maximum conductors in 1/2 IN conduit 11/17/2005
Just a quick question. How many #12 THHN solid or stranded wire can be
pulled through 1/2" EMT ?
Thank You.
Mitch, East Elmhurst, NY
9 conductors
Table C1 Maximum Number of Conductors or Fixture Wires in Electrical Metallic Tubing (EMT) (Based on Table 1, Chapter 9)
Kerny 11/11/2005
Hi, found your site I find it very interesting, have found myself reading your Q&A and I'm very impressed have a few rookies on board and have recommended they visit once and awhile,
The question that had the term kerny in it, baffled me why, you would not know what that was, but then realized you may not have grown up with a father that worked and electrical line crew. Kerny was misspelled its kernsy or (split Bolt) kernsy was the name brand the only name. This reminds me of air admittance valve and ( studder vent).
Timothy D Evans
Chief Building Official, Town Of Leland NC
Well Chief Evans:
I want to thank you for that correct information. I have been in the business for over 38 years and I never caught that era. Most contractors and inspectors were taught layman's terms and never the correct code terms. If you see any more incorrect words, please let me know.
Thanks, Ed Stubbs
CATV homeruns 11/11/2005
Hi Ed,
Thanks so much for your informative web site. I have one quick question....
The NEC doesn't seem to contain any design provisions for low-voltage wiring. Is there any reference to TIA-570, requiring home runs for low voltage wiring (Cable TV, Telephone, etc.)?
Thanks,
Roman
I'm sorry to inform you that the NEC is not a design publication. However, It does contain information on the minimum installation and safety requirements. Article 725, 760, and 800.
90.1 Purpose.
(A) Practical Safeguarding. The purpose of this Code is the practical safeguarding of persons and property from hazards arising from the use of electricity.
(B) Adequacy. This Code contains provisions that are considered necessary for safety. Compliance therewith and proper maintenance will result in an installation that is essentially free from hazard but not necessarily efficient, convenient, or adequate for good service or future expansion of electrical use
(C) Intention. This Code is not intended as a design specification or an instruction manual for untrained persons.
725.1 Scope.
This article covers remote-control, signaling, and power-limited circuits that are not an integral part of a device or appliance.
760.1 Scope.
This article covers the installation of wiring and equipment of fire alarm systems including all circuits controlled and powered by the fire alarm system.
800.1 Scope.
This article covers telephone, telegraph (except radio), outside wiring for fire alarm and burglar alarm, and similar central station systems; and telephone systems not connected to a central station system but using similar types of equipment, methods of installation, and maintenance.
Romax wiring 11/11/2005
I am a home inspector in Illinois. Recently had a client call me back three months after an inspection to tell me all of the romex wiring in her basement, and garage must be replaced, as electricians told her is was not a safe method of wiring, and did not comply with building codes.
I need a professional opinion here. Is or is not Romex a safe and reliable method of wiring in a home? is or is not Romex found in about 85% of the homes across the country? Should a home inspector who covers multiple towns, multiple counties, multiple villages, etc. be expected to know what the specific building codes are for each location he inspects? I know for a fact that this location falls under the National Electric Code 2002 version, according to their building codes posted on the municipality's web site. Doesn't the NEC 2002 plainly state that Romex is perfectly acceptable? Why then is this electrician trying to make her spend $5000 to replace all of the wiring with rigid conduit, when the code states Romex is acceptable?
Any advice, or input would be greatly appreciated as I am going to have to resolve this dispute hopefully avoiding the courtroom!
Sincerely,
John
Your observations are correct. NM-B is approved for installation on all dwelling in the 2002 NEC. You have stated that the State of Illinois has adopted the 2002 NEC. I am sure that there are some municipalities that have some restrictions on the use of NM-B. One thing to remember, if you are inspecting in multiple counties, you need to know if the municipalities have local ordinances. Do some homework. You mentioned that you were called back three months later after an inspection. Are you talking about your inspection or an Illinois Inspectors inspection? Was the wiring existing or were you hired to inspect the electricians work? If the wiring is existing, the electrician can't force anyone to rewire their home. Is there a local government inspection department? If there is, give them a call. Maybe you should get the customer to get two more licensed electricians to look at the job and give her an estimate. I don't think court will be an issue.
Difference of single & double pole breaker 11/7/2005
Hello,
I'm adding 3 circuits to my home panel. I see there are single and double pole breakers but I don't know the difference and when either are required.
A) What is the difference between a single pole 20 amp circuit breaker and a double pole circuit breaker?
B) Are there any NEC codes that restrict the use of one over the other.
Thanks
Since you are questionable about the difference from a single pole breaker and a double pole breaker, I am questionable about you installing any breakers inside your home panel. My advice is for you to have a qualified electrician to install the breakers. Opening a panel without electrical knowledge can cause you a serious shock or burn if not installed correctly.
I can give you a simple explanation of a single and double pole breaker. 99% of the receptacle outlets in your home are 120 volts and are protected by a single pole breaker (or fuse from older panels). Those single pole breakers protect your kitchen, bedrooms, lights, bathrooms, outside outlets, basement, garage, etc. When you see a double pole breaker, they are used to control a circuit that requires twice the voltage. 120 volts on each breaker will give you 240 volts (220 volts or 230 volts in some states), depending on the power company. If you look at the label in the panel, it should tell you what circuit it is protecting. Most circuits that use 240 volts are your water heaters, range, oven, cook tops, air conditioners, electric heaters, furnace, dryer, outside pool pumps, etc.
The panel can contain up to a maximum of 42 total (combination single or double pole) breakers without violating the connected load or the manufactures maximum listing or label of the panel. Be safe.
Tankless water heater 11/2/2005
Ed,
I just found your site today, thank you for all the information. I want to install a LP Tankless water heater. The unit I am looking at is sealed combustion unit, with outside air intake. Is there a minimum clearance it needs to be from my electrical service panel?
Thank You,
Craig Lee
I don't think your question is complete. Is the Tankless water heater located in front of the service equipment? All service equipment shall have a minimum of 3 foot clearance in front and 30 inches wide.
110.26 Spaces About Electrical Equipment.
Sufficient access and working space shall be provided and maintained about all electric equipment to permit ready and safe operation and maintenance of such equipment. Enclosures housing electrical apparatus that are controlled by lock and key shall be considered accessible to qualified persons.
(A) Working Space. Working space for equipment operating at 600 volts, nominal, or less to ground and likely to require examination, adjustment, servicing, or maintenance while energized shall comply with the dimensions of 110.26(A)(1), (2), and (3) or as required or permitted elsewhere in this Code.
Disconnecting means 11/1/2005
Ed,
If you have a fused disconnect switch at a central point of distribution feeding a single building is there a need for your panel being fed by this disconnect to have a main breaker?
Thank You,
Don
No! Since this is a single building or structure, a second disconnect shall not be required. If you think about it, a single family dwelling or a single service building has a main fuse or circuit breaker outside and a feeder panelboard inside with up to 42 branch circuits per panel.
If you had more than one building or structure on the same property under single management, then you have to comply with Article 225.30. You will have to have a single disconnect in or near the panelboard.
225.30 Number of Supplies.
Where more than one building or other structure is on the same property and under single management, each additional building or other structure served that is on the load side of the service disconnecting means shall be supplied by one feeder or branch circuit unless permitted in 225.30(A) through (E). For the purpose of this section, a multiwire branch circuit shall be considered a single circuit.
225.31 Disconnecting Means.
Means shall be provided for disconnecting all ungrounded conductors that supply or pass through the building or structure.
225.32 Location.
The disconnecting means shall be installed either inside or outside of the building or structure served or where the conductors pass through the building or structure. The disconnecting means shall be at a readily accessible location nearest the point of entrance of the conductors. For the purposes of this section, the requirements in 230.6 shall be permitted to be utilized.
Outlet under kitchen counter 10/26/2005
I wish to install outlets on the bottom of my kitchen cabinets. They will be slightly more than 20 inches above the counter which I believer to be an issue. The intent is to avoid making holes in my back splash.
The best way to connect them would appear to make runs from the existing outlet boxes (which will be covered over with Granite) and bring them thru the wall between the granite and cabinet bottoms.
How many code violations do you see?
I am going to do it one way or the other so could you recommend what I need to do for the run from the existing boxes to the outlets that will be on the bottom of the cabinets.
Thank you very much for this assistance
G. M.
I see several violations from your statement. You already made the comment "slightly more than 20 inches above the countertop". I don't know what "slightly" means to you. The existing boxes shall be accessible if the conductors remain in the boxes. The conductors shall be no less than 1 1/4 inches back into the stud wall and there shall be a junction box for the receptacles or plug mold strips not greater than 20 inches above the countertop.
300.15 Boxes, Conduit Bodies, or Fittings — Where Required.
Where the wiring method is conduit, tubing, Type AC cable, Type MC cable, Type MI cable, nonmetallic-sheathed cable, or other cables, a box or conduit body complying with Article 314 shall be installed at each conductor splice point, outlet point, switch point, junction point, termination point, or pull point, unless otherwise permitted in 300.15(A) through (M).
(A) Wiring Methods with Interior Access. A box or conduit body shall not be required for each splice, junction, switch, pull, termination, or outlet points in wiring methods with removable covers, such as wireways, multi outlet assemblies, auxiliary gutters, and surface raceways. The covers shall be accessible after installation.
300.4 Protection Against Physical Damage.
Where subject to physical damage, conductors shall be adequately protected.
(A) Cables and Raceways Through Wood Members.
(1) Bored Holes. In both exposed and concealed locations, where a cable- or raceway-type wiring method is installed through bored holes in joists, rafters, or wood members, holes shall be bored so that the edge of the hole is not less than 32 mm (11/4 in.) from the nearest edge of the wood member. Where this distance cannot be maintained, the cable or raceway shall be protected from penetration by screws or nails by a steel plate or bushing, at least 1.6 mm (1/16 in.) thick, and of appropriate length and width installed to cover the area of the wiring.
(B) Small Appliances.
(C) Countertops. In kitchens and dining rooms of dwelling units, receptacle outlets for counter spaces shall be installed in accordance with 210.52(C)(1) through (5).
(5) Receptacle Outlet Location. Receptacle outlets shall be located above, but not more than 500 mm (20 in.) above, the countertop. Receptacle outlets rendered not readily accessible by appliances fastened in place, appliance garages, or appliances occupying dedicated space shall not be considered as these required outlets.
600 volt disconnect 10/23/2005
Can you mount a 600v 30amp disconnect switch directly over a 480 volt grinder by code ?
By code, you would be in violation of 110.26
110.26 Spaces About Electrical Equipment.
Sufficient access and working space shall be provided and maintained about all electric equipment to permit ready and safe operation and maintenance of such equipment. Enclosures housing electrical apparatus that are controlled by lock and key shall be considered accessible to qualified persons.
Key to understanding 110.26 is the division of requirements for spaces about electrical equipment in two separate and distinct categories: working space and dedicated equipment space. Working space generally applies to the protection of the worker, and dedicated equipment space applies to the space reserved for future access to electrical equipment and to protection of the equipment from intrusion by non electrical equipment. The performance requirements for all spaces about electrical equipment are set forth in the first sentence. Storage of materials that blocks access or prevents safe work practices must be avoided at all times.
(A) Working Space. Working space for equipment operating at 600 volts, nominal, or less to ground and likely to require examination, adjustment, servicing, or maintenance while energized shall comply with the dimensions of 110.26(A)(1), (2), and (3) or as required or permitted elsewhere in this Code.
The intent of 110.26(A) is to provide enough space for personnel to perform any of the operations listed without jeopardizing worker safety. These operations include examination, adjustment, servicing, and maintenance of equipment. Examples of such equipment include panelboards, switches, circuit breakers, controllers, and controls on heating and air-conditioning equipment. It is important to understand that the word examination, as used in 110.26(A), includes such tasks as checking for the presence of voltage using a portable voltmeter.
Minimum working clearances are not required if the equipment is such that it is not likely to require examination, adjustment, servicing, or maintenance while energized. However, “sufficient” access and working space are still required by the opening paragraph of 110.26.
404.8 Accessibility and Grouping.
(A) Location. All switches and circuit breakers used as switches shall be located so that they may be operated from a readily accessible place. They shall be installed so that the center of the grip of the operating handle of the switch or circuit breaker, when in its highest position, is not more than 2.0 m (6 ft 7 in.) above the floor or working platform.
Smoke alarm interconnect 10/23/2005
I recently installed three alarms in my house, 120 volt, battery backup, w/ interconnect. I have inadvertently hooked my power supply to the yellow interconnect wire. Now that I have properly wired it the units work individually, but not all at once, Could I have damaged the alarms interconnect by doing this?
Greg
Are you referring to alarms or smoke detectors? There is a great possibility of a definite confirmed maybe, that you may have damaged the smoke detector or alarm system. I have connected many alarms and smoke detectors, but didn't have a yellow wire. If you hook up smoke detectors that are interconnected, the three wire on the 120 volt side is black white and red. The other system is a heat detector. I'm not sure we are on the same page. Find the instructions manual and check your wiring method.
HVAC receptacle 10/23/2005
Hi. Who job is it to put the maintenance recp outside for a new air conditioner unit. Is it the HVAC person installing the unit or an electricians job. This is on an apartment complex. Thanks Vince
Well Vince, that is a question only the State and local jurisdiction can answer. The State of Georgia has given the HVAC contractors the right to install a branch circuit from a panelboard to the equipment they are installing. They are limited a structure or building service that is limited to a 200 amp, single phase. They cannot install a service or feeder just to install a branch circuit.
Reciprocal bathlight/fan 10/17/2005
Hello,
Thanks,
Tom
The switch requirement doesn't change with or without a window. Some municipalities want the fan/light to be on one switch so that you can air out the bathroom at the same time the light is on. Without the window, you won't be able to remove the odor if the fan is not on. I personally install one switch in the bathrooms I wired up. We both know some people think their stuff don't stink.
AFI'S 10/10/2005
Mr. Stubbs,
Just had a new breaker box installed in my home. Electrician installed 3 AFI'S. Now I notice I have a hum coming from the box. When I turn off the AFI's the hum stops. Is this normal for AFI's to be a little noisy? Never have been exposed to these before, house had a fuse box originally. Could this just be the nature of the beast? Any information would be greatly appreciated.
Thank you,
Charles
|
The AFI'S you are referring to are Arc-fault breakers. There are a few arc-fault breakers that are a little noisy. There are several possibilities that could be wrong. A defective breaker, loose connection, or a bad ballast connected on that circuit. Hopefully you had a qualified electrical contractor that can figure out the problem.
Conductor cross-section 10/6/2005
Where would I find the cross-sectional area of bare, stranded or solid conductors ? Is there a specific place to look ? Trying to learn the code Thank you.
Table 9 Alternating-Current Resistance and Reactance for 600-Volt Cables, 3-Phase, 60 Hz, 75°C (167°F) — Three Single Conductors in Conduit (Page 625 in the soft paper back) 2002 NEC
Receptacle calculation 10/3/2005
Greetings.
In calculating load, I assume that "multiple outlet on a single yoke" is
a duplex receptacle and it is calculated as one? In other words is a
duplex receptacle considered as one or two outlets?
Thank you,
Michael
It is only counted as one outlet. The total calculated load on this outlet device is 180 volt amps. See diagram below
220.3 Computation of Branch Circuit Loads.
(B) Other Loads — All Occupancies.
(9) Receptacle Outlets. Except as covered in 220.3(B)(10), receptacle outlets shall be computed at not less than 180 volt-amperes for each single or for each multiple receptacle on one yoke. A single piece of equipment consisting of a multiple receptacle comprised of four or more receptacles shall be computed at not less than 90 volt-amperes per receptacle.
Transfer switch 9/28/2005
Ed -
I saw your notes on minimum space around the breaker panel as 30" minimum.
Unfortunately, the builders put my breaker panel on a basement wall that is
30" wide, bounded by a concrete wall on one side and a window opening on the
other. I am going to install a transfer switch for a generator, but don't
know how best to do this. Do I mount a panel on the concrete wall adjacent
to the main panel and connect the two via an elbowed/90 degree piece of
conduit?
Thanks in advance!
Chris
Dear Chris:
I'm sorry I didn't answer your question sooner. I just noticed the question was on the web site, but no answer. The location of the panelboard is not a problem at all. As long as you maintain your 3 foot clearance in front of the equipment and 30 inch wide elbow room you'll be OK. see main breaker clearance
Pool lights 9/26/2005
how far do lights have to be from the edge of the swimming pool
Raul
San Antonio TX.
680.22 Area Lighting, Receptacles, and Equipment.
(B) Luminaries (Lighting Fixtures), Lighting Outlets, and Ceiling-Suspended (Paddle) Fans.
(1) New Outdoor Installation Clearances. In outdoor pool areas, luminaries (lighting fixtures), lighting outlets, and ceiling-suspended (paddle) fans installed above the pool or the area extending 1.5 m (5 ft) horizontally from the inside walls of the pool shall be installed at a height not less than 3.7 m (12 ft) above the maximum water level of the pool.
Townhouse buildings 9/23/2005
what can be done about county electrical inspection departments that are commonly miss interpreting the code ? they have no amendments and will not discuss the issues other than to say that's the way the see it. These are common things which they are getting wrong . badly they really seem lost.
2) when slab grounding a 6 unit Townhouse building using a meter pack on one end
is one stub out of building steel correct. If all the footing steel is tied together the units will drop 2 feet per unit
(1). This is more of a legal question then a code question. There will always be some lack of knowledge of code in any municipality where there is no mandatory training or interest in their departments. It's not easy for some inspectors if they have to inspect more than one type of inspection. See: The Authority Having Jurisdiction
(2). Your question is not clear to me. You said the meter pack is on one side, but are the mains over there also?
Since Townhouses have come to light in the building it has become a great nightmare for contractors and inspectors to understand the proper wiring method. I will try to make it clear to all that reads this article. If the footing rebar's are bonded together, you still have to bond at each unit. I have yet to see the builder tie the footings together on firewall footings.
I'll narrow it down to two choices: Meter packs without mains. Meter packs with mains.
1. Meter packs without mains shall be bonded to the rebar in the footing or two ground rods (250.56). All of the service conductors shall be 3- wire insulated conductors (not SEU) run outside of each unit (like a back to back service) to a main overcurrent device inside. Each unit shall have the grounding electrode bonded to the rebar at that location. According to article 250.32 they are separate buildings. (What a pain!)
250.32 Two or More Buildings or Structures Supplied from a Common Service.
(A) Grounding Electrode. Where two or more buildings or structures are supplied from a common ac service by a feeder(s) or branch circuit(s), the grounding electrode(s) required in Part III of this article at each building or structure shall be connected in the manner specified in 250.32(B) or (C). Where there are no existing grounding electrodes, the grounding electrode(s) required in Part III of this article shall be installed.
(B) Grounded Systems. For a grounded system at the separate building or structure, the connection to the grounding electrode and grounding or bonding of equipment, structures, or frames required to be grounded or bonded shall comply with either 250.32(B)(1) or (2).
2. Meter packs with 6 main disconnects shall also be bonded to the rebar from the main or to two ground rods (250.56). You can still run a 3- wire service conductor or a 4-wire feeder conductor (not SEU or SER) run outside of each unit. You still have to have mains inside each unit and bond to the rebar at that unit. If you installed a 3-wire cable, the equipment ground and the neutral bar shall be bonded together with the main bond screw installed. If you installed a 4-wire cable (which is more costly), you have to bond the equipment ground to the rebar. Ground rods shall only be required in the same manor if no other grounding means were available.

(D) Disconnecting Means Located in Separate Building or Structure on the Same Premises. Where one or more disconnecting means supply one or more additional buildings or structures under single management, and where these disconnecting means are located remote from those buildings or structures in accordance with the provisions of 225.32, Exception Nos. 1 and 2, all of the following conditions shall be met:
(1) The connection of the grounded circuit conductor to the grounding electrode at a separate building or structure shall not be made.
(2) An equipment grounding conductor for grounding any non–current-carrying equipment, interior metal piping systems, and building or structural metal frames is run with the circuit conductors to a separate building or structure and bonded to existing grounding electrode(s) required in Part III of this article, or, where there are no existing electrodes, the grounding electrode(s) required in Part III of this article shall be installed where a separate building or structure is supplied by more than one branch circuit.
(3) Bonding the equipment grounding conductor to the grounding electrode at a separate building or structure shall be made in a junction box, panelboard, or similar enclosure located immediately inside or outside the separate building or structure.
I need help 9/10/2005
1. What size thwn copper conductors are required to supply continuous load of 13 amp.
2. the minimum length of free conductor required by NEC to be left in the boxes for splices is___measured from the point in the box where it emerges from its raceway. and what codes it can be found.
3. a circuit breaker that reads 20 on the handle can only be expected to trip___ times before it requires replacement.
(1). Since you are asking about a singe branch circuit, the calculation shall be 125% of the continuous load. 1.25 X 13 = 16.25 amps.
210.19 Conductors — Minimum Ampacity and Size.
(A) Branch Circuits Not More Than 600 Volts.
(1) General. Branch-circuit conductors shall have an ampacity not less than the maximum load to be served. Where a branch circuit supplies continuous loads or any combination of continuous and noncontiguous loads, the minimum branch-circuit conductor size, before the application of any adjustment or correction factors, shall have an allowable ampacity not less than the noncontiguous load plus 125 percent of the continuous load.
The conductor size shall be based on the wiring method you are using. Since you mentioned THWN copper, I will assume that the wiring terminals and the devices are rated in the 75 degree column. Table 310.16 shows that a 14 awg conductor can be used. The overcurrent protection is another concern. It can be larger than a 15 amp overcurrent device if it is a motor or allowed elsewhere in this code.
240.4 Protection of Conductors.
(D) Small Conductors. Unless specifically permitted in 240.4(E) through (G), the overcurrent protection shall not exceed 15 amperes for 14 AWG, 20 amperes for 12 AWG, and 30 amperes for 10 AWG copper; or 15 amperes for 12 AWG and 25 amperes for 10 AWG aluminum and copper-clad aluminum after any correction factors for ambient temperature and number of conductors have been applied.
(2). 300.14 Length of Free Conductors at Outlets, Junctions, and Switch Points.
At least 150 mm (6 in.) of free conductor, measured from the point in the box where it emerges from its raceway or cable sheath, shall be left at each outlet, junction, and switch point for splices or the connection of luminaries (fixtures) or devices. Where the opening to an outlet, junction, or switch point is less than 200 mm (8 in.) in any dimension, each conductor shall be long enough to extend at least 75 mm (3 in.) outside the opening.
Exception: Conductors that are not spliced or terminated at the outlet, junction, or switch point shall not be required to comply with 300.14.
(3). This question can only be answered by the manufacture of that breaker. How many times can a cell battery be recharged? Every manufacture has a different level of reliability.
Paralleled conductors 9/1/2005
IF branch circuit, feeder, or service conductors must be paralleled because of the high magnitude of full load current, what is the minimum wire size that can be paralleled ? Thank you and GOD Bless.
310.4 Conductors in Parallel.
Aluminum, copper-clad aluminum, or copper conductors of size 1/0 AWG and larger, comprising each phase, neutral, or grounded circuit conductor, shall be permitted to be connected in parallel (electrically joined at both ends to form a single conductor).
Conductors connected in parallel, in accordance with 310.4, are considered a single conductor with a total cross-sectional area of all conductors in parallel. Therefore, if individual conductors are tapped from conductors in parallel, the tap connection must include all the conductors in parallel for that particular phase. Tapping into only one of the parallel conductors will result in unbalanced distribution of tap load current between parallel conductors. This will result in one of the conductors carrying more than its share of the load, which can cause overheating and conductor insulation failure. For example, if a 250-kcmil conductor is tapped from a set of two 500-kcmil conductors in parallel, the splicing device must include both 500-kcmil conductors and the single 250-kcmil tap conductor.
No outside disconnect 8/23/2005
Mr. Stubbs, just came across your web site - lots of great information. I didn't see my question answered, so hopefully you can help. I'm looking at upgrading my service to 400 amp and have a question regarding bonding of the grounded conductor. Currently, the panel is located in the garage with the meter on the opposite side of the wall. There is no outside disconnect and the main is located in the panel.
I assume do to the close proximity of the meter to the panel, no outside disconnects will be required. Am I correct here? What I plan to do is use a 320 amp double lug meter socket and locate 2- 200 amp panels on the opposite side of the wall with the main breakers in the breaker panels. I assume I would need to attach the conductor from the ground rod in the meter socket itself. Can I attach the ground rod at the meter socket and run 3 wire cable to each 200 amp panel, using a bonding jumper in each panel? Or must I separate the ground and neutral in the panels and run 4 wire cable to the meter socket?
Thanks in advance for any help you can provide.
-Derek
Hampton, Georgia
From the information you have given me, it looks like you're going in the right direction. I will make a few points to you since I can't see your service. There are several articles you need to look at to insure that you are in compliance.
(1) I noticed you said that you are installing a 320 amp double lug meter socket. The chances that your demand will exceed 320 amps is very slim, but possible. I don't know why you are going to a 400 amp service. (See 100 amp vs 200 amp)
(2) Be sure that both mains are grouped together in the garage. Article 230.70 & 230.72 and maintain 3 foot clearance in front of the main services.
(3) Make sure that your local jurisdiction doesn't have a local ordinance restricting the new installation.
(4) If there are water pipes in the garage, they shall be bonded. Article 250 grounding
You don't need the 4 wire cable coming from the meter enclosure. Where are you going to terminate an equipment ground and a grounded conductor (neutral) in your main? Remember, if they both terminate on the ground bar in the meter and the ground in the main, wouldn't they be paralleled? If they are paralleled, they shall be the same size, type, insulation, etc. See 310.4 parallel conductors. I don't know of any manufactures that make the equipment ground the same size as the neutral. One more point, did you notice on SEU Service (3-wire) cable that the grounded conductor is bare and the SER Feeder (4-wire) cable has an insulated neutral conductor?
Main breaker Clearance 8/15/2005
Dear Mr. Stubbs,
I am planning on installing a media central wiring box for my
video/Internet/phone system, and I'd like to flush mount it underneath
(between the same two studs as) my flush-mounted main breaker panel in
my finished garage. As a result it will be approx 5 inches away from the
edge of the main panel. I am uncertain if the 36 x 30 rule would be
violated - does it apply to something that is flush mounted? The media
center cover sticks out about 1/4" from the wall.
Thanks,
Glenn
Not a problem at all. The Clearance required by Article 110.26 and 110.32 are for a safe working Clearance in front of the equipment and basically elbow room to side of the equipment to be clear from making contact with a grounded surface. Since the equipment you plan to install will be flush to the finish surface, you still have the 30 inch wide space that is required.
Send us your code question: Mailto: edstubbs1@comcast.net
Restaurant outlets 8/11/2005
What does the code require for receptacles in restaurants. How many are required for general use and how far apart? Not for kitchen.
Not like single and multifamily dwellings, or motels and hotels, there are no requirements except for design by the owners or the engineers. Where dwelling are required, the NEC requires convenient outlets to reduce the use of extension cords and multiple plug-in adaptors. Commercial restaurants outlets are installed by demand and general use receptacles are the choice of the owner, engineer and the contractor. There is no minimum or maximum distance between outlets. Article 220 does require a general-use outlet of 1 watt /sq. ft. calculation for areas without outlets and 180 VA per outlet where outlets will be installed. Article 210 gives required outlet location and distance.
220.1 Scope.
This article provides requirements for computing branch-circuit, feeder, and service loads.
220.3 Computation of Branch Circuit Loads.
Branch-circuit loads shall be computed as shown in 220.3(A) through (C).
(B) Other Loads — All Occupancies. In all occupancies, the minimum load for each outlet for general-use receptacles and outlets not used for general illumination shall not be less than that computed in 220.3(B)(1) through (11), the loads shown being based on nominal branch-circuit voltages.
(9) Receptacle Outlets. Except as covered in 220.3(B)(10), receptacle outlets shall be computed at not less than 180 volt-amperes for each single or for each multiple receptacle on one yoke. A single piece of equipment consisting of a multiple receptacle comprised of four or more receptacles shall be computed at not less than 90 volt-amperes per receptacle.
This provision shall not be applicable to the receptacle outlets specified in 210.11(C)(1) and (2).
(10) Dwelling Occupancies. In one-family, two-family, and multifamily dwellings and in guest rooms of hotels and motels, the outlets specified in (1), (2), and (3) are included in the general lighting load calculations of 220.3(A). No additional load calculations shall be required for such outlets.
III. Required Outlets
210.50 General.
Receptacle outlets shall be installed as specified in 210.52 through 210.63.
210.52 Dwelling Unit Receptacle Outlets.
This section provides requirements for 125-volt, 15- and 20-ampere receptacle outlets. Receptacle outlets required by this section shall be in addition to any receptacle that is part of a luminaries (lighting fixture) or appliance, located within cabinets or cupboards, or located more than 1.7 m (51/2 ft) above the floor.
210.60 Guest Rooms.
(A) General. Guest rooms in hotels, motels, and similar occupancies shall have receptacle outlets installed in accordance with 210.52(A) and 210.52(D). Guest rooms meeting the definition of a dwelling unit shall have receptacle outlets installed in accordance with all of the applicable rules in 210.52.
As I stated before, Part III of Chapter 2 doesn't have minimum required outlets for other then dwelling occupancies.
Underground wiring 8/3/2005
hello.
I am new to this game and would appreciate your thoughts.
I am building a house. About 1600 square feet. Nothing unusual in regard to power requirements...200 amps.
The meter pole is 150 away. I would like to run underground wiring from the pole to the house disconnect. My question is what size wire would I need for this so that I would not be concerned about voltage drop? Some say 2, others 3. Which is bigger? I cant find anything on the web t |